Get the Right Foremen on the Bus – Last Planner® Implementation Series

Foremen for each functional area standing at a zone map in the project trailer
Read 9 min

This is the start of our takt and Last Planner implementation series. At Lean Takt and Elevate, we’re getting really, really good at creating takt plans, creating flow, optimizing schedules, and building the look-ahead, the weekly work plans, the zone maps, and the roadblock tracking maps. I’d say we’re probably the best in the business. Kevin and I have done most of the implementation ourselves, and now our trained process improvement engineers are taking it on. It’s one thing to have a great schedule. It’s another thing to have flow in the field. So I created a list and called it the Last Planner implementation checklist.

Short answer: Last Planner implementation in the field starts with getting the right foremen on the bus: clean, safe, and organized, close to the work, trained in lean, and assigned one per phase or functional area. Without the right foremen in the right seats, the last planners can’t collaborate, buy in, and commit, and your systems won’t work.

Is It Last Planner or Takt Steering and Control?

Let me confirm something. The Last Planner System is predicated on using a master scheduling system, which would be takt. Or you don’t have to call it Last Planner at all. Call it takt with takt steering and control. I don’t care whether you call it that or Last Planner with takt as the master scheduling system. The two concepts pair together, and there are so many similarities on the short-interval production scheduling side.

When I say Last Planner, I mean the point, probably after the pull plan, when the last planners are involved in the schedule as the last people in the planning cycle at the last moment: the weekly work plan and the day plan. So yes, you have this takt plan. But do you have your zone maps and takt plan up on the wall? Are you tracking roadblocks, focusing on handoffs, and implementing zone control? Those are the things I care about, and that was the reason I created this list. See Last Planner System Explained.

What Has to Be Ready First?

I just presented this at the decentralized conference with Jesse Hernandez and a fantastic group of presenters. Implementing the Last Planner System is predicated on having:

  • A takt plan and zone maps
  • A procurement log
  • A logistics plan
  • A trailer and signage design
  • An organizational chart
  • A risk and opportunity register
  • A macro and normal-level takt plan, all formatted and ready to implement with boots on the ground

This is where the rubber meets the road.

What Are the First Five Steps?

I think there are about 27 items on the list, and I’ll probably get it to 25. Here are the first five:

# Implementation step
1 Get the right foremen on the bus
2 Understand your phases and functional areas
3 Make sure you have foremen for all functional areas
4 Decide on a meeting schedule that’s going to be a good one
5 Decide on your conference room, trailer, and visuals

What Do You Expect From a Foreman?

On the Elevate website, under field resources and lean signage, there’s a list I published a long time ago called foreman expectations. A few of them:

  • Be located in the jobsite trailer or on site, not running around from job to job.
  • Bring materials to the site just in time.
  • Enforce company and project safety rules from the trade partner safety manual.
  • Keep crew operations clean and organized.
  • Do not let materials touch the ground. Everything on wheels, pallets, racks, or in some kind of container.
  • Spend time every morning teaching about the eight wastes, 5S or 3S, and implementing lean concepts.
  • Participate as a project team member in the Last Planner System and the morning and daily huddles.
  • Encourage crews to come up with lean improvements.
  • Post material, equipment, and supply deliveries visibly and schedule them with the project team.
  • Attend a pre-construction meeting before the work and research the plans and specifications.

The bottom line is the foreman must be clean, safe, and organized, have proximity with the team, understand lean principles, and be willing to communicate and participate in the right meetings and systems.

What Happens With the Wrong Foreman?

There are people out there, and I love them and their moms love them, who aren’t yet qualified to be crew leaders or foremen but are in that position. They don’t have proximity, they don’t know lean, and they aren’t clean, safe, and organized. That is not going to work. You might need to do it out of necessity, but it’s like a bad rash.

I’ve said it before and I’ll say it again: I’ve never seen a wrong-cultural-fit foreman problem go away. Am I blaming people? No. I’m blaming behaviors, culture, the process, and the system. A misalignment is a process, system, culture, and behavior problem, and it won’t go away. You have to have the right foremen for your systems to work.

Why One Foreman per Functional Area?

On a civil project, you need foremen for crews that are spread out. On a utility project in a public right-of-way, one foreman leads pipe installation, another supervises the paving behind, maybe another does traffic control.

On the bioscience research laboratory, we had exteriors, interiors, and a basement. For the interiors on the top four floors and the basement, there had to be a separate foreman or lead for each. Otherwise they weren’t in the right huddles, because eventually superintendents break those huddles out, and a foreman can’t be in multiple areas or too many meetings at once and be effective.

Our contract conclusions list says all foremen must be approved by the on-site team and comply with the requirements or be removed. The project is broken into geographical areas for operational control, each supervised by a superintendent and a field engineer, so each trade must provide a dedicated foreman or lead for each area.

Should You Interview Foremen?

We interview trade partners, employees, and for projects. We’re going to have to start interviewing foremen, being very selective and making sure they’re trained. If you’re saying, Jason, there aren’t a lot of trained foremen, then let’s get to training people. I have a book for you, Elevating Construction Foremen. I wouldn’t be above telling bidding trade partners months ahead that their foremen must read this book and be interviewed by the project team before the trade partner is selected.

On the bioscience research laboratory, all foremen were required to be OSHA 30 trained and all workers OSHA 10 trained. We needed 380 workers. Built in Phoenix, it would have taken about 210. That’s the difference in skill in the geographical area we were in. It wasn’t easy, but we made it happen. You can do this.

Yes, the last planners are the last people in the planning cycle, the people closest to the work, and where improvement starts. They need to collaborate, buy in, and commit. But for that to happen, you need the right foremen on the bus and in the right seats, separated by functional area or phase. Read How to Be a Good Construction Foreman.

A listener wrote that the superintendent book is the best tool in the toolbox. That made my night.

So here is the challenge. List every phase and functional area on your project. Next to each, write the name of the dedicated foreman or lead. Any blanks are your first implementation gap.

Bottom line: Get the right foremen on the bus and in the right seats, because without them your systems won’t work.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

On we go.

Takt and Last Planner Implementation series:
This is the first episode of the series.
Next: Phases & Functional Areas

FAQ

What has to be in place before implementing the Last Planner System in the field?

A takt plan and zone maps, a procurement log, a logistics plan, a trailer and signage design, an organizational chart, a risk and opportunity register, and a macro and normal-level takt plan, all formatted and ready to put boots on the ground.

What are the first five steps of Last Planner implementation?

1. Get the right foremen on the bus. 2. Understand your phases and functional areas. 3. Make sure you have foremen for all functional areas. 4. Decide on a good meeting schedule. 5. Decide on your conference room, trailer, and visuals.

What makes the right foreman for a lean project?

The foreman must run clean, safe, and organized work, have proximity to the team, understand lean principles, be willing to communicate and participate in the right meetings and systems, and be a cultural fit, trained and onboarded to the project’s systems.

People Also Read:
The Last Planner System
Foreman Series: Operational Excellence
What Is a General Foreman in Construction?
Morning Foreman Huddles Are Just Team Huddles

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.